SIDDHI KRISH DEVELOPERS

6 registered projects on our index, 5 completed with occupancy, 1 still within it.

Counted from the MahaRERA public register — not from the builder's own past-experience declaration. Earliest registration here is from 2017. Covers Thane — the districts indexed so far, so a builder active elsewhere may have more.

6

Registered projects

5

Completed with OC

0

Past declared date

0

Lapsed or flagged

Of the projects whose date has arrived

5 of 5 have completion recorded on MahaRERA. None are outstanding.

Declared possession dates that moved

1 of 6 project has a possession date different from the one first registered. The largest change is 5 years, on HIGHLAND HAVEN BUILDING 6F MIST-B PHASE 5.

Size of the portfolio

413 homes across the projects indexed here, where unit counts are on record.

Have they kept to the dates they registered?

Across 6 projects with a declared possession date.

5
Date never pushed back
0
Pushed back up to a year
1
Pushed back over a year

MahaRERA publishes the date a promoter declared, not the date an occupancy certificate was issued — so this measures revisions to their own commitment, which is what the register can show.

Every registered project (6)

Looking at one of these?

A builder's record is context, not a verdict on the flat you're buying. Run the safety check on the specific project before you pay anything.

Check a project free

Compiled from the MahaRERA public register. These are counts of the promoter's own legally-required disclosures — we describe the record, not the company. Possession dates are what the promoter declared, not a guarantee. Verify on maharera.maharashtra.gov.in.

Developers often register each project under a separate company, so one group may appear here under more than one name, and this page shows only the projects registered under “SIDDHI KRISH DEVELOPERS”. How we compile this · Report a correction

Check a project