Marigold Meadows

Greenfield Estates Pvt Ltd · Wakad, Pune

RERA ID P51900067890

LapsedUpdated 01 Jun 2026
90
High risk

High delay risk — read the orders and talk to existing buyers before committing.

Key signals

RERA status
Lapsed
RERA registered
30 Jun 2021
Registered possession
30 Jun 2021
Revised possession
31 Dec 2024
Delayed by
5 yrs
Extensions
3
Overall construction
48% · 9/22 slabs
Completion / Occupancy
CC ✓ · OC ✗
Total units
180
Complaints filed
41

How the score is built

Transparent, additive factors from public data — total 90/100.

RERA registration status32 / 35

Registration has lapsed — a serious red flag.

Delay vs registered possession25 / 25

59 months past the originally registered possession date.

Construction progress8 / 15

48% complete · 9/22 slabs.

Buyer complaints15 / 15

41 complaint(s) across 180 units (23%).

Order compliance10 / 10

2 order(s) passed but not complied with.

Litigation0 / 10

None on record.

Orders passed

  • refund· 05 Nov 2023Not complied

    Refund with interest ordered for 6 withdrawing allottees.

  • interest· 18 Jun 2024Not complied

    Delay interest ordered for continuing allottees.

  • penalty· 02 Mar 2025Pending

    Penalty for non-compliance with earlier order.

Illustrative sample data shown for demonstration. The Risk Score is an interpretive aid derived from factual public signals; it is not legal advice and not a judgment on any promoter. Always verify documents on the official MahaRERA portal and consult an advocate.