Horizon Square
Meridian Buildcon · Thane West, Thane
RERA ID P51600077665
High delay risk — read the orders and talk to existing buyers before committing.
What you can do
Key signals
How the score is built
Transparent, additive factors from public data — total 95/100.
Registration revoked by the Authority.
65 months past the originally registered possession date.
35% complete · 8/24 slabs.
73 complaint(s) across 260 units (28%).
2 order(s) passed but not complied with.
None on record.
Orders passed
- refund· 19 May 2023Not complied
Refund with interest ordered for multiple allottees.
- possession· 28 Feb 2024Not complied
Directions for handover; not honoured.
- penalty· 14 Oct 2024Pending
Registration revoked; association allowed to complete.
Illustrative sample data shown for demonstration. The Risk Score is an interpretive aid derived from factual public signals; it is not legal advice and not a judgment on any promoter. Always verify documents on the official MahaRERA portal and consult an advocate.